Key Performance Areas
KPIs | MEASURE | TARGET | |
---|---|---|---|
1 | As MEDQ delegate, the time taken to set a pre-lodgement meeting following request |
Less than or equal to 5 business days Note: no statutory timeframe | 90% |
2 | As MEDQ delegate, the time taken to issue pre-lodgement meeting minutes following meeting |
Less than or equal to 2 business days
Note: no statutory timeframe | 90% |
3 |
As MEDQ delegate, assessment fees advised as a component of being considered properly made
Note: excludes regulatory assessment fees where external consultant input is required |
Less than or equal to 2 business days
Note: no statutory timeframe | 95% |
4 | As MEDQ delegate, initial engineering assessments completed |
Less than or equal to 10 business days
Note: no statutory timeframe | 10 Days |
5 | As MEDQ delegate, the time taken to issue an information request and confirm public notification requirement |
Less than or equal to 20 business days
Note: relevant statutory timeframe is 20 business days | 90% |
6 | As MEDQ delegate, the time taken to issue an initial further issues request |
Less than or equal to 20 business days
Note: no statutory timeframe | 90% |
7 | As MEDQ delegate, percentage of Development Applications decided without an information request |
No target - actual to be reported
Note: no statutory requirement | NA |
8 | As MEDQ delegate, percentage of Development Applications decided without a further issues request |
No target - actual to be reported
Note: no statutory requirement | NA |
9 |
As MEDQ delegate, the time taken to decide an application
Note: excludes time taken for public notification and applicant to respond to any information request or provide further issues response |
Less than or equal to 30 business days of decision-making period
Note: relevant statutory timeframe is 40 business days | 80% |
10 |
As MEDQ delegate, the time taken to decide an application
Note: excludes time taken for public notification and applicant to respond to any information request or provide further issues response |
Less than or equal to 40 days of decision-making period
Note: relevant statutory timeframe is 40 business days | 90% |
11 |
As MEDQ delegate, the total time taken for applications by type to proceed from properly made to decision
Note: includes time taken for public notification and applicant to respond to any information or further information requests |
No target - median number of business days to be reported
Note: no statutory requirement | NA |
12 | As MEDQ delegate, the total time taken to assess and decide applications for Compliance Assessment |
No target - median number of business days to be reported
Note: no statutory requirement | NA |
13 |
As MEDQ delegate, the total time taken to complete Plan Sealing assessments
Note: KPI measured from the date all information received |
Less than or equal to 10 business days
Note: no statutory timeframe | 95% |
14 | As MEDQ delegate, the total time taken to issue Infrastructure Charges Notices |
Less than or equal to 10 business days
Note: no statutory timeframe | 90% |
15 | As MEDQ delegate, the total time taken to issue Infrastructure Offset Determinations issued |
Less than or equal to 20 business days
Note: no statutory timeframe | 90% |
16 | As MEDQ delegate, the total time taken to issue Certification Procedures Manual acknowledgements |
Less than or equal to 10 business days
Note: no statutory timeframe | 90% |
17 | Level of customer satisfaction with the pre-lodgement process | Customer rating satisfied or above. | 90% |
18 | Level of customer satisfaction with overall performance as MEDQ delegate | Customer rating satisfied or above. | 70% |

Last updated: 30 June 2025